ISBT Extesion Project at Transport Nagar
- Posted by admin
- On October 15, 2018
- 0 Comments
1. Mussoorie Dehradun Development Authority is developing Extension of ISBT housing scheme at Transport Nagar Phase 1 and Phase 2 in Dehradun.
2. Authority is coming with 132 MIG (Stilt +6) Units at Transpor Nagar Phase 1 at Saharanpur Road and 368 EWS & LIG (G+3) Units at Transport Nagar Phase 2.
3. The EWS& LIG units are getting developed for the banificiaries of River Front Development Project.
4. Area of site for MIG is around 8364 SqM. and for EWS & LIG is around 11431.55 SqM .
5. The distance from ISBT is about 1.3 KM.
6. Construction agency is UPRNN Unit 4.
7. The housing scheme is financialy supported by HUDCO.
Status:-
On Both the sites structure work is on progress. Sample flat is getting ready for public. In MIG almost 45% work and in EWS& LIG almost 55% has been completed.